Commercial Windows & Doors Ltd company name
Specialists in the refurbishment of 
aluminium & glass facades
020 8885 8585 

Specialists in aluminium and glass facades

Over 35 years of experience

CSCS accredited


Project: Atlantic Court, Kings Road, SW3

Project: Atlantic Court, Kings Road, SW3                                                             

Project: Atlantic Court, Kings Road, SW3

Client: PJ Harte   

                                                                                                                                           

  • Water testing: (pre-works) to 10 No. Test areas were carried out to pinpoint ingress areas.               
  • Replacing curtain wall caps and pressure plates: We removed the cover caps, pressure plates and single, eagle gaskets and fitted new Schueco dual gaskets, foil backed butyl tape, pressure plate and cover cap finished to a matching PPC RAL colour.
  • Renewing silicone seals: All existing silicone seals previously applied to the glazed curtain wall system and components were thoroughly removed and renewed. 
  • Curtain wall airflow/drainage mouldings. 25% of missing airflow/drainage mouldings were replaced with new. 
  • Replacement glazing: 16 No. large curved, 5 shaped, 40 rectangle and 4 curved Okalux double glazed units were removed and reglazed with new.                                                                                           
  • Restorative clean: All PPC finishes with the exception of the new caps were restoratively cleaned using our specialist fluids. 
  • Front entrance: The front entrance was beyond restorative cleaning, so we carried out a full, 10 year guaranteed, paint respray.
  • Copings: All defective coping sealants were thoroughly cleaned off and replaced with new.                                               
  • Glazed pitched roof: The outer caps, pressure plates and Eagle gasket were removed and new Schueco dual gaskets, foil backed butyl tape, mullion pressure plates and cover caps finished to a standard PPC ral colour were fitted along with chamfered, water throw off, transom PPC pressure caps. Defective perimeter sealant was thoroughly removed, and new sealant was applied.                                 
  • Water testing: (post works) The 10 No. pretested areas were retested resulting in water no longer entering the building.


Please contact us if you have any similar requirements.

Contact
Share by: